Standard, normal and emergency changes: how to tell them apart

Short answer: A standard change is low risk, repeatable and pre-approved, so it runs from a documented procedure without a meeting. A normal change is assessed for risk and approved before it runs, by a change advisory board (CAB) or a delegated approver depending on the risk. An emergency change is needed now to stop or prevent serious harm, gets a fast approval from a small group, and is reviewed afterwards. If nothing is being lost and nothing serious is about to happen, it is not an emergency.

Change classification sounds like paperwork. It is really a way to spend review effort where the risk is. Google’s Site Reliability Engineering book reports that roughly 70% of outages are due to changes in a live system (Introduction). Treat every change the same and you either slow routine work to a crawl or wave risky work through. Three categories, used honestly, avoid both.

The three types side by side

Type Risk Approval Typical lead time Examples
Standard Low, well understood Pre-approved once; each run is logged None beyond the schedule Routine patching from a tested baseline, adding a user to a standard group, replacing a failed drive in a redundant array
Normal Low to high, assessed each time Delegated approver for low risk; CAB for medium and high Days, set by your CAB cycle Firewall rule changes, a database upgrade, a new monitoring agent on production servers
Emergency Usually high, but delay is worse Small emergency group, by phone or chat Minutes to hours A fix for an active P1, an urgent security patch for a vulnerability being exploited

The examples are typical, not automatic. Patching a critical database cluster may well be a normal change even where desktop patching is standard.

Standard changes: earn the status

A standard change is the reward for doing something safely and predictably. Before you approve one, check that:

  • it has been done successfully several times as a normal change;
  • the steps, checks and rollback are written down and anyone qualified can follow them;
  • the impact if it goes wrong is low and the rollback is quick;
  • someone owns the procedure and reviews it on a schedule.

Keep a list of approved standard changes, and remove an item from the list if it causes an incident until the procedure has been fixed. A healthy change process moves routine work into the standard list over time, which frees the CAB to look at changes that need attention.

Normal changes: a simple risk score

For normal changes, a quick risk score decides who approves. Rate impact and likelihood from 1 to 3 and multiply them.

Rating Impact if it goes wrong Likelihood it goes wrong
1 One non-critical service, few users, outside business hours Done many times before, tested in a non-production environment, rollback under 15 minutes
2 One critical service or a whole team, or during business hours Done before but not recently, partly tested, or rollback takes up to an hour
3 Several critical services, customers or a whole site First time, untested, many dependencies, rollback over an hour, or no clean rollback

The product can only be 1, 2, 3, 4, 6 or 9. A practical mapping:

  • 1 or 2, low risk: a delegated approver such as the service owner signs off.
  • 3 or 4, medium risk: the CAB reviews it, and it runs in an agreed maintenance window.
  • 6 or 9, high risk: the CAB reviews it with the plan, test evidence and a timed rollback, and stakeholders are told in advance.

Two rules make the score more useful than the arithmetic suggests. First, the person raising the change scores it and the approver checks the score, so nobody marks their own work low risk without a second look. Second, record the score. After a few months you can compare scores with which changes actually failed and adjust the criteria.

The rollback question

Chapter 11 of Modern IT Infrastructure and Operations gives a blunt test for CAB meetings: when someone says a change is quick and nothing should go wrong, ask exactly how it will be undone, and decline the change if the engineer cannot explain how to roll it back in under fifteen minutes. “Should” is not a plan. A rollback that has never been rehearsed belongs in the likelihood score.

Emergency changes: close the loophole

The emergency path exists so that a fix for an active outage is not stuck waiting for next Tuesday’s CAB. It is also the easiest path to abuse. The same chapter of the book draws the line clearly: an emergency is when the business is losing money or data now. A missed submission deadline is not an emergency; it waits for the next cycle. If late planning can use the emergency route, the emergency route soon becomes the normal one.

Three habits keep it honest:

  1. Name a small emergency approval group and make sure one member can always be reached.
  2. Record every emergency change, even when it was approved by phone, and link it to the incident it fixed.
  3. Review every emergency change at the next CAB: was it really an emergency, did it work, and does anything need to become a normal change to finish the job?

How to tell if it is working

  • Change failure rate. DORA defines change fail rate as the ratio of deployments that require immediate intervention after they are deployed (DORA metrics). DORA measures deployments, but the same idea works for every change. Track it by change type. Standard changes should fail rarely; if they do not, review the list.
  • Share of emergency changes. A rising share usually means planning problems, not more emergencies.
  • Incidents caused by unrecorded changes. Every post-incident review should ask whether a change was involved and whether it had a record. “No ticket, no change” only works if someone checks.

Templates and further reading

The Change Risk Assessment Matrix takes the same idea further: it scores each change on several risk factors, turns the total into an approval route, and rates any change with no possible rollback, or a data change that cannot be reversed, as at least high risk. It is part of the Change Management Toolkit, which also includes a CAB meeting pack, a rollback plan template and a change calendar. To start with something free, download the change request form.

Chapter 11 of Modern IT Infrastructure and Operations covers the three change categories, CAB responsibilities and how change connects to incident and problem management. For setting incident priority, see Incident priority matrix: how to set P1 to P4.

Sources: Google, Site Reliability Engineering, Introduction. DORA, DORA metrics. Al Alousi, Modern IT Infrastructure and Operations, chapter 11. The scoring scheme is an example to adapt.

Before you download

These templates are general starting points, not legal, compliance, financial or other professional advice. They are not tailored to your organization.

You are responsible for adapting, checking and approving anything you use. The files are provided as is, without warranty, and 365 Technical LLC is not liable for how they are used.

By downloading, you agree to the Terms of use (opens in a new tab).